Mountjoy has been appointed to undertake the Design and Build of a brand-new youth centre at Eldon Way, in Littlehampton, West Sussex. The new building will stand directly across from the old centre, which is due to be demolished.
The new building will provide two large open spaces for sporting and community activities, as well as a central circulation area, kitchen and Multi Use Games Area (MUGA) and play area.
Site operations begin on the new K2 Youth Centre at Eldon Way, Littlehampton. Early works included the establishment of the car park and the preparation of the MUGA.
Mountjoy welcomed guests from Littlehampton Town Council and Arun District Council to officially kick-off the works.
The tarmac on the MUGA is completed, with fencing to follow and white lines to be painted towards the end of the project ready for use.
External fencing surrounding the MUGA is completed.
Foundations for the new community centre have been poured in preparation for construction to begin.
The team begin the construction of the steel frame structure of the building.
The steel frame structure of the building is successfully completed.
The ground floor concrete slab of the building has now been poured.
Brickwork and blockwork walling to the external and internal walls begins.
As brickwork continues, the installation of scaffolding begins to the outside of the building.
Exterior brickwork is complete to a height of 2.7m.
Scaffolding is completed, allowing for brickwork, cladding, and roof works to proceed.
As work progresses, the Thermalite internal walls near full height.
Kalzip roof liner is installed over the main hall, ready to recieve roof overalying rof sheet, with openings installed for Velux windows.
Top hats and rails are installed on the roof of the new K2 Centre.
Velux windows are installed within the roof.
Timber infills are installed between steels on the roof. This will provide a substructure for external cladding.
The Birdcage scaffold is removed from the interior of the main hall.
Flow Screed is laid, providing a level surface ready for the application of floor finishes.
Indicative markings are measured on internal walls, preparing for electrical installations.
Kalzip roof is complete, with Velux windows installed.
For added security, temporary windows are fitted prior to final window installation.
Internal blockwork is complete, ready for plastering.
Metal studs are installed, ready for 1st fix Mechanical and Electrical installations.
Insulation installed to eaves, ready for timber cladding
Strips of timber (battens) are installed to the building exterior, ready for timber cladding to be installed on top.
Works begin on installing Thermowood cladding to the exterior of the K2 Youth Centre.
A trench is dug to receive service ducts.
Installation of Thermowood cladding to the exterior of the centre is completed.
Scaffold has been removed from the building exterior. A cherry picker is used on site to complete any high works.
Insulation is installed to the interior of the building. This will later be covered when the internal walls are plasterboarded.
Grasscrete blocks are laid to allow for easy access to the rear of the building.
Plastering to the interior of the Main Hall is underway.
Large windows have been installed within the Main Hall with protection added to the glass to avoid scratches.
Plastering works within the Main Hall are completed. A cherry picker is used to paint the roof steels.
The base layer outside the entrance to the centre is prepared, ready to receive paving slabs.
The Main Hall's walls and steel work is painted.
Plastering work has been completed to the walls of the K2 Centre's kitchen.
An opening is created within the wall of the K2 Centre kitchen to serve as a service hatch.
A feature wall is painted within the Main Hall of the building.
A patio is laid to the rear of the K2 Centre.
Barriers are installed and roadworks are started to create the entrance to site.
Plastering works underway to head of door frames in the main hall.
An opening is formed within the K2 Centre's reception, ready for a glazed screen to be installed.
Ceiling lights are installed within the main hall.
Vinyl flooring is laid within the main hall,
External works including the installation of fencing, tarmacadam, and the undertaking of soft landscaping works are underway.
A glazed screen is installed within the Reception area of the centre.
A polyurethane floor is installed within the main hall.
Doors are installed for cupboards within main hall of the K2 Youth Centre.
Automatic double doors are installed to the rear of the building, leading to the patio and garden area.
The K2 Youth Centre's WC facilities are successfully completed.
A seating area and storage area for bicycles is installed to the front of the centre.
Rear view of K2 Youth Centre, showing PV panels on roof, patio and garden area, and fencing around the MUGA (Multi-Use Games Area).
The K2 Youth Centre in Eldon Way, Littlehampton is now complete. The centre will provide facilities for sporting and community activities for people within the local community.